Procedure During Construction in UDCPR 2020

Apr 06, 2024

UDCPR 2020 Chapter 2 is all about Development Permission and Commencement Certificate as per mentioned in the UDCPR 

 

This is Applicable to all Planning Authorities and Regional Plan Areas except the Municipal Corporation of Greater Mumbai, Other Planning Authorities/Special Planning Authorities/ Development Authorities within the limits of the Municipal Corporation of Greater Mumbai, MIDC, NAINA, Jawaharlal Nehru Port Trust, Hill Station Municipal Councils, Eco-sensitive/Eco-fragile region notified by MoEF & CC, and Lonavala Municipal Council in Maharashtra.

 

Rule No. 2.8 Procedure During Construction

 

2.8.1  Owner/Developer/Architect/Town Planner/Engineer/Structural Engineer/supervisor or any licensed technical person's Responsibilities in their respective domain.

 

i) Neither granting of the development permission nor the approval of the drawings and specifications, nor the inspections, made by the Authority during the erection of the building shall, in any way relieve the Owner/Developer/Architect/Town Planner/Engineer/Structural Engineer/Supervisor or any licensed technical person, of such building/development from full responsibility for carrying out the work in accordance with the requirements of these regulations and safety norms as prescribed by the bureau of Indian Standards.

 

ii)  Every owner/developer shall :

 

a) Permit the Authority or his representative to enter the building or premises for which permission has been granted at any reasonable time to enforce these Regulations.

 

b) Submit the certificate for the execution of work as per structural safety requirements and give written notice to the Authority regarding the completion of work.

 

c) Give written notice to the Authority in case of termination of services of a Technical professional engaged by him.

 

2.8.2 Results of Test

 

Where tests of any materials are made to ensure conformity with the requirements of these regulations, records of the test data shall be kept available for inspection during the construction of the building and for such period thereafter as may be required by the Authority.

 

2.8.3 Display Board

 

As soon as the development/building permission is obtained, the owner/developer shall install a "Display Board" on a conspicuous place on-site indicating the following details :-

 

i)  Name and address of the owner, developer, and all concerned licensed persons

 

ii)  Survey number/city survey number of land under reference

 

iii)  Order number and date of grant of development/building permission/redevelopment permission issued by the Authority.

 

iv) Built-up area permitted

 

v)  RERA registration no

 

vi) Software QR Code for the Project generated in online building permission.
Such a Display Board shall not be required for individual plot holders' individual buildings.

 

2.8.4 Plinth Checking

 

The owner shall give intimation in the prescribed form in Appendix - F to the Authority after the completion of work up to the plinth level. This shall be certified by the Architect/licensed Engineer/Supervisor with a view to ensuring that the work is being carried out in accordance with the sanctioned plans. After such intimation, the construction work shall be carried out further. The officers of the Authority, who are empowered to grant development permission and subordinate officers to him, shall each, inspect about 10% of such plinth-certified cases.

 

2.8.5  Deviation During Construction

 

If during the construction of a building, any deviation of a substantial nature from the sanctioned plans is intended by way of internal or external additions, sanction of the Authority shall be necessary. A revised plan showing the deviation shall be submitted and the procedure laid down for the original plans shall apply to all such amended plans. Any work done in contravention of the sanctioned plans, without prior approval of the Authority, shall be deemed as unauthorized. However, any changes made within the internal layout of a residential or commercial unit, which does not violate FSI or other regulations, shall not be treated as unauthorized. Such changes shall be incorporated into the plan along with the completion certificate. Provided that revised permission may also be granted after the completion of work before obtaining a full occupancy certificate.

 

Related Regulations to Rule No. 2- 

 

You can visit our other blog on Regulation 2 through the below-mentioned links:

 

Commencement of Work in UDCPR 2020

 

Grant or Refusal of Permission in UDCPR 2020

 

Various Regulations in Chapter 2 in UDCPR 2020

 

Discretionary Powers and Relaxations In Specific Cases in UDCPR 2020

 

Discretionary Powers Interpretation in UDCPR 2020

 

Procedure for Obtaining Development Permission, Building Permission, Commencement Certificate in UDCPR 2020

 

Permission from the Planning Authority is Mandatory in UDCPR 2020